Benchtop Incubators - Planer CT37 STAX


Planer CT37 STAX Installation Guide



Status Monitoring:


  • Step 1: Equipment needed

  • Step 2: Find Planer CT37 STAX external alarm port

  • Step 3: Link Planer CT37 STAX to ViGIE

  • Step 4: Configure an alarm and perform a test



Step 1: Equipment needed 


-    Airo Sensor 202041

-    Planer CT37 STAX Equipment Status Cable/Adapter



Step 2: Find Planer CT37 STAX external alarm port 


The Alarm Port is located at the back of the unit.





Step 3: Link Planer CT37 STAX to ViGIE 


Connect the Planer CT37 STAX and the External Status Adapter to the Airo Sensor 202041 External adapter, using the NO (Normally Open) contacts.

Then the Adapter is ready to connect to the Analog Alarm Output from Planer CT37 STAX .


Step 4: Configure an alarm and perform a test 


1st - Find your sensor using the ViGIE Platform and configure an alarm profile.

2nd - Check if the Planer CT37 STAX status match the ViGIE platform


Planer CT37 STAX OK  = ViGIE OK


If the status is mismatched (eg: Equipment Alarm but ViGIE OK) please raise a ticket with ViGIE Helpdesk Team
.
To: helpdesk@vigiesolutions.com
Subject: Status Sensor Label Swap

My Airo Sensor 202041 with Serial Number: (please fill in) needs a Label Swap.



3rd - Simulate an event


After simulate an event, please ensure that a new ViGIE Alarm was created/sent. 

Then a recovery should be tested as well, performing a status follow-up using ViGIE Platform.


Whenever the equipment alarms, the external alarm output will be activated.



Temperature Probe Monitoring:


External temperature probe port:




Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons